An abbreviated design and construction timeline for the new Crete Public Library and community building has been updated as of Oct. 16, 2018. (This timeline is subject to change.)

 

(May - June 2018: Engineering plans and specifications)

 

(July 2018: Construction bidding)

 

(August 2018: Pre-construction staking, permits, mobilization)

 

September - October 2018: Site finish grading

 

October - November 2018: Utilities and power installation

 

October - December 2018: Footings and foundations

 

November 2018 - January 2019: West retaining wall

 

December 2018 - February 2019: Structural steel construction

 

January - May 2019: Roofing

 

February - October 2019: Interior construction

 

December 2019: Finish construction

 

December 20, 2019: Estimated completion date

 

December 21-31, 2019: Estimated closure of old library

 

January 2, 2020: Estimated opening of new library facilities

 

Spring 2020: Off-site hard and soft-scape installation