Timeline as of 23 October 2017

 

Please note that this timeline is subject to change

 

October-November 2017 - Architectural and Engineering Conceptual/Schematic Design

October-November – Hazardous Materials Removal

November-December 2017 - Architectural and Engineering Design Development

January -March 2018 - Demolition of Existing Structure and Site Rough Grading

March 2018 - Fundraising Complete, Final Construction Scope Determined

March-May 2018 - Engineering Plans and Specifications

May-June 2018 - Construction Bidding

July 2018 - Pre-Construction Staking, Permits, Mobilization

July-August 2018 - Site Finish Grading and Utilities

August-November 2018 - Structural Exterior Construction

December 2018-March 2019 - Interior Construction

April-October 2019 - Finish Construction

August-October - Off-Site Hard and Soft-Scape Installation